Estimating that most large - scale projects need something on the order of Can $ 1 billion to become economically viable, Ball says that the Boundary Dam project wouldn't be able to go forward without a steady stream of revenue from the sale of CO2.

Not exact matches

SaskPower has had challenges with its $ 1.5 - billion Boundary Dam coal - fired power carbon capture and storage project.
Boundary Dam will be the first CCS project built on a commercial - scale power station.
POWER's Editor Interviewed About Carbon Capture and Sequestration In November 2015, POWER Editor Gail Reitenbach gave a luncheon keynote presentation at the Carbon Management Technology Conference on SaskPower's Boundary Dam 3 carbon capture and sequestration (CCS) project.
A natural gas turbine can reach about 350, while a coal plant equipped with carbon capture — such as the innovative Boundary Dam CCS project in Canada — can release less than 130 kg of CO2 per megawatt - hour.
The integrated carbon capture and storage (ICCS) project at the Boundary Dam Power Station has scooped up its first major award, even though it has been fully operational for less than three months.
Large - scale CCS projects in the power sector are now a reality, demonstrated by: * The world's first large - scale power sector CCS project — the Boundary Dam Integrated Carbon Capture and Sequestration Demonstration Project in Canada (CO2 capture capacity of 1 Mtpa)-- becoming operational in October 2014 * Commissioning activities on a new - build 582 megawatt (MW) power plant beginning at the Kemper County Energy Facility in Mississippi (US, CO2 capture capacity of 3 Mtpa) with CO2 capture expected to commence in the first half of 2016 * The Petra Nova Carbon Capture Project at the W.A. Parish power plant near Houston, Texas (US, CO2 capture capacity of 1.4 Mtpa) entering construction in July 2014, with CO2 capture anticipated by the end oproject — the Boundary Dam Integrated Carbon Capture and Sequestration Demonstration Project in Canada (CO2 capture capacity of 1 Mtpa)-- becoming operational in October 2014 * Commissioning activities on a new - build 582 megawatt (MW) power plant beginning at the Kemper County Energy Facility in Mississippi (US, CO2 capture capacity of 3 Mtpa) with CO2 capture expected to commence in the first half of 2016 * The Petra Nova Carbon Capture Project at the W.A. Parish power plant near Houston, Texas (US, CO2 capture capacity of 1.4 Mtpa) entering construction in July 2014, with CO2 capture anticipated by the end oProject in Canada (CO2 capture capacity of 1 Mtpa)-- becoming operational in October 2014 * Commissioning activities on a new - build 582 megawatt (MW) power plant beginning at the Kemper County Energy Facility in Mississippi (US, CO2 capture capacity of 3 Mtpa) with CO2 capture expected to commence in the first half of 2016 * The Petra Nova Carbon Capture Project at the W.A. Parish power plant near Houston, Texas (US, CO2 capture capacity of 1.4 Mtpa) entering construction in July 2014, with CO2 capture anticipated by the end oProject at the W.A. Parish power plant near Houston, Texas (US, CO2 capture capacity of 1.4 Mtpa) entering construction in July 2014, with CO2 capture anticipated by the end of 2016.
Saskatchewan Power in Canada will start its $ 1.35 billion Boundary Dam coal - fired CCS project this year, capturing a million tonnes annually of carbon dioxide in what it says is the world's first post-combustion coal - fired CCS project.
Carbon capture experts say two important projects will open soon in North America: the Southern Company's Kemper County plant in Mississippi, which will burn coal to make electricity and provide carbon dioxide for oil recovery, and the Boundary Dam coal plant in Saskatchewan, which will do the same.
A keynote address was given by Mike Monea, SaskPower President of Carbon Capture and Storage (CCS) Initiatives, who provided an update on the Boundary Dam CCS project.
The Boundary Dam in Saskatchewan captures carbon dioxide from a coal power station and sells the gas to Canadian oil company Cenovus, which uses it for an EOR project.
The project transforms the aging Unit # 3 at Boundary Dam Power Station near Estevan, Saskatchewan into a reliable, long - term producer of 110 megawatts (MW) of base - load electricity and reduces greenhouse gas emissions by one million tonnes of CO2 each year.
Notable mandates: Successfully fended off a class action certification motion against Canadian National Railway over alleged overcharging for grain carriage; acted for Federated Co-operatives Ltd. in its $ 138 - million acquisition of oil company Triwest Exploration Inc.; Saskatchewan counsel to Wal - Mart Canada Realty Inc. and SmartCentres Realty Inc. on the $ 200 - million sale of shopping centres to Great - West Life Assurance Co. and London Life Insurance Co.; represented Northern Property REIT in $ 70 - million purchase of Nunavut properties; advised Saskatchewan Power Corp. on its $ 1.24 - billion Boundary Dam Integrated Carbon Capture and Storage Demonstration Project.