Defended trial court's holding that, in light of the express terms of the parties» contract, the Town of Southington's election to terminate the contract for convenience did not preclude it from recovering liquidated damages
against the
contractor because that right arose as
soon as the substantial completion date passed and continued to accrue until the termination of the contract.